by ECC | Mar 14, 2019 | Latest Victories
M1 today received another victory against Anfi Group. It was revealed again that the accommodation was not properly identified. The judge ruled that the contract be deemed null and void and ordered the resort to payout €17,428 euros. Two lawyers from M1 worked on this...
by ECC | Mar 12, 2019 | Latest Victories
After an initial court decision that the case did not fall under Spanish jurisdiction, M1 Legal appealed the decision which was reversed. The defence argued that the case should not be heard in Spain claiming the contract falls under English law. The appeal judge...
by ECC | Feb 28, 2019 | Latest Victories
It continues to be a snowball effect with Anfi contracts being thrown out. The contract revealed it was in perpetuity i.e. no end date and the property description was not properly stated. The judge ruled that the contract be deemed null and void and ordered Anfi to...
by ECC | Feb 27, 2019 | Latest Victories
The clients had two contracts, Cala Pi Maintenance S.L. and Noarre S.L. The case was initiated by their resort Cala Pi processing a claim against our client for unpaid maintenance fees totalling over €12,000. M1 legal stepped in on the grounds that the company...
by ECC | Feb 25, 2019 | Latest Victories
After an initial court decision that the case did not fall under Spanish jurisdiction, M1 Legal appealed the decision which was reversed by the Malaga Court of Appeal. The defence argued that the case should not be heard in Spain claiming that the contract fell under...